Shell's Prelude to remain offline this quarter

SHELL chief Ben van Beurden told reporters overnight that its flagship Prelude offshore LNG facility in north Western Australia would remain offline through the first quarter of 2022.

Teething troubles: van Beurden

Teething troubles: van Beurden

The company was ordered by the offshore regulator, NOPSEMA, to shut down the facility in December, following a small fire caused by an electrical fault which tripped the facility's main power, forcing the company to use back up diesel generators and evacuate staff. 

A report from the regulator has since suggested a power outage could have led to ‘catastrophic failure' on the vessel.

Shell CEO Ben van Beurden told reporters following last night's quarterly results that the company encountered an electrical fault in the battery systems associated with the uninterruptible power supply. 

"Prelude is going through some teething troubles but bearing in mind this is a unique asset of course, quite a unique challenge as you can imagine," he said. 

"We need to resolve these issues comprehensively and carefully before we restart." 

He said Western Australia's tight border control was making it "difficult to get people in", due to the 14-day quarantine requirements.  

"To get a vendor specialist in means that person will have to quarantine for weeks before they can go on board, so these problems compound the issue a little bit but also we want to make sure when we restart that we have resolved the problem." 

He said the company was working closely with NOPSEMA to fix the issues on board the facility, but it would likely remain offline for "most of Q1". 

A NOPSEMA spokesperson told Energy News this morning Shell has been holding weekly update meetings with NOPSEMA on its progress restoring the facility. 

To resume production, Shell must complete an investigation into the December incident and create and execute a timely plan to implement all nessesary corrective measures, according to NOPSEMA. 

"Shell must also demonstrate to NOPSEMA that the facility can operate safely in the event of powe loss before production can recommence," the spokesperson said.  

"It is currently expected that compliance with the General Direction could occur sometime in late Q1 2022, with production only able to resume once that has occurred."

The shutdown ended the 11-month production streak Shell's A$24 billion facility was on, after being shut in for most of 2020 due to a slew of technical issues. 

The facility hit its nameplate capacity of 3.6 million tonnes of LNG per annum in the middle of last year for the first time since start up. 

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.

editions

ENB Cost Report 2021

This industry-wide report aims to understand current cost levels across the energy industry