THE six gas wells drilled to date in Incremental Petroleum and Otto Energy's Edirne Gas project in Western Turkey have discovered sufficient gas to proceed to front-end engineering design.

Incremental said the wells drilled in 2007 and 2008, along with a fourth well spudded today, would be placed on production with first sales expected before mid 2009.

The Arpaci-2 well is the fourth well of a five well drilling program in the Thrace Basin and is expected to reach planned total depth of around 480m by early next week, Incremental said.

Arpaci-2 is 650km northeast of Arpaci-1, which was drilled in January 2006.

Incremental holds a 55% stake in the Edirne licence, while Otto Energy has 35% and Turkish company Petraco holds the remaining 10%.