OPERATIONS

LNG plant development delayed

Indonesia's Pertamina has announced that the construction of a ninth LNG plant in East Kalimantan...

This article is 22 years old. Images might not display.

The delay has been attributed to the fact that Indonesia has only managed to secure a contract for 1.2 million tonnes of LNG to be shipped to South Korea, which is around half of the proposed plant's capacity.

Pertamina official, Inoenoe, confirmed that the construction had been delayed but added that "the [Indonesian] government expects to secure more contracts in the coming months to pave the way for the construction of the new plant." It is believed that Inoenoe was alluding to the signed preliminary agreement signed between Indonesia, Mexico and the US to buy Indonesian LNG.

Should all go according to plan, the plant will probably be constructed by a consortium led by Japan's Chiyoda Co Ltd with financing provided by Japan's Mitsubishi Corp.

TOPICS:

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

Future of Energy: The Role of Batteries Report 2026

The role of batteries and storage in Australia’s energy transition

editions

Future of Energy Report: Nuclear Power in Australia 2024

Energy News Bulletin’s new report examines what the energy and resources industry thinks of the idea of a nuclear-powered Australia.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.