Initial earthworks have been completed by Technip Oceania and civil works, foundation and concreting are underway.
The shore crossing pipe is almost completed. The 4 inch and 20 inch holes have been drilled and the casing pipe is currently being pushed through, with work expected to be completed early next month.
The offshore Thylacine platform jacket and topsides are being fabricated in the Malaysian state of Johor by Malaysia Shipyard & Engineering.
The first steel was cut earlier this year and it will be loaded out for shipping to the Thylacine field around October this year.
The 70km of 20-inch pipeline is being coated in Indonesia after being manufactured in Nagoya, Japan. Half of the four-inch pipe has been manufactured to date in Wakayama, Japan by Sumitomo.
Interest holders in the T/30P and Vic/P43 joint ventures covering the Thylacine and Geographe discoveries include Woodside Energy 51.55%, Origin Energy Resources 29.75%, Benaris International NV 12.70% and CalEnergy Gas (Australia) 6%.