McConnell Dowell back on NGP

MCCONNELL Dowell is back on board as the construction partner for Jemena’s $800 million Northern Gas Pipeline, just over two months after it was dropped from the project.

 The last shipment of pipe for our $800 million Northern Gas Pipeline landing in the NT ahead of the start of construction.

The last shipment of pipe for our $800 million Northern Gas Pipeline landing in the NT ahead of the start of construction.

McConnell Dowell was dismissed from building the Northern Territory section of the NGP after Jemena decided to re-sequence the construction to start the Queensland portion first to give it time to negotiate...

Start a free trial to continue reading this article
Already have an account?  
Subscribe now
MORE ON THIS TOPIC

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.

editions

ENB Cost Report 2021

This industry-wide report aims to understand current cost levels across the energy industry

editions

ENB Social Licence Report 2021

In its second year, this research now includes trends and new findings surrounding impacts and responses as the energy industry seeks to secure and maintain a social licence to operate.