NGP machinations revealed

JEMENA let McConnell Dowell go from the Northern Gas Pipeline in March simply because it was yet to secure traditional owner approval and could not meet the start date, but now that they’re back on board first gas is expected by the end of 2018, <i>Energy News</i> has learned.

 The last shipment of pipe for our $800 million Northern Gas Pipeline landing in the NT ahead of the start of construction.

The last shipment of pipe for our $800 million Northern Gas Pipeline landing in the NT ahead of the start of construction.

McConnell Dowell was dumped in March as the contractor to build the Northern Territory portion of the NGP when protracted negotiations with TOs forced Jemena to re-sequence and to start building the Queensland...

Start a free trial to continue reading this article
Already have an account?  
Subscribe now

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.

editions

ENB Cost Report 2021

This industry-wide report aims to understand current cost levels across the energy industry

editions

ENB Social Licence Report 2021

In its second year, this research now includes trends and new findings surrounding impacts and responses as the energy industry seeks to secure and maintain a social licence to operate.