Armour up and running 

ARMOUR Energy’s Kincora gas project in Queensland’s Surat Basin has achieved production and sales of nine terrajoules day, while LPG and condensate production has exceeded expectations putting the Roma project in a better place after some earlier hiccups. 

Armour up and running  Armour up and running  Armour up and running  Armour up and running  Armour up and running 

Armour delivers on 9TJpd target from Kincora

The final cost of the Kincora restart and associated infrastructure that includes the Wallumbilla pipeline facility was recently announced at $10 million, far higher than the initial $6.