THE cost of building a liquefied natural gas plant has doubled over the past two years, according to ConocoPhillips new ventures opportunity manager Mark Nelson.

LNG plants responsible for cost rise

"This could be one reason why many LNG projects have not been able to reach final investment decisions in their development phase as LNG suppliers are seeing this cost growth," he told the SEAAOC conference in Darwin yesterday.

He also indicated that ConocoPhillips is still targeting first production from a second train at the company's Darwin LNG facility by around 2014-15 with gas from the Sunrise field and Caldita.

The Darwin LNG facility at Wickham Point currently produces 3.5 million tonnes of LNG per annum but has the land and the necessary approvals for an expansion to 10MMtpa.

TOPICS:

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.

editions

ENB Cost Report 2021

This industry-wide report aims to understand current cost levels across the energy industry