Santos to drill 10 Narrabri wells

SANTOS offered a little more detail on its Narrabri CSG project at yesterday’s investor briefing day, noting it planned to drill 10 appraisal wells prior to sanction in 2023 and is looking at a reduced capital spend on the project for its first phase out to 2026. 

Santos to drill 10 Narrabri wells Santos to drill 10 Narrabri wells Santos to drill 10 Narrabri wells Santos to drill 10 Narrabri wells Santos to drill 10 Narrabri wells
 
The wells come in at a cost of A$90 million in total, putting a steep price tag on each individual CSG well after the CEO Kevin Gallagher earlier outlined cost cuts to the project, telling